Usually, yes — often on two counts. A two-storey extension generally triggers section 6 through its deeper foundations near the neighbour’s building, and…

By Karmjit Grewal · 2 min read · Reviewed 2026-09-26

The short answer

Usually, yes — often on two counts. A two-storey extension generally triggers section 6 through its deeper foundations near the neighbour’s building, and section 2 because the upper floor is frequently tied into, built off, or raises the party wall. You will usually need both a notice of adjacent excavation and a party structure notice before starting.

Why it matters

The upper storey is what sets a two-storey extension apart. Carrying the new floor and roof often means inserting beams into the party wall and bonding new masonry to it — clearly a section 2 work, which needs a party structure notice under section 3, served two months ahead. The foundations are usually deeper than a single-storey, strengthening the section 6 case (one month). You may also build the flank wall on the boundary (section 1). On a terrace, both neighbours can be affected. The award deals with support, method, scaffolding access, protection and a schedule of condition.

What to do now

  • If your neighbour does dissent, suggest a single agreed surveyor acting fairly for both of you — cheaper and faster than two. Coburns recommends this wherever possible.
  • Get structural and foundation drawings.
  • Identify where the new structure meets the party wall.
  • Apply the section 6 tests.
  • Serve a party structure notice (two months) and an excavation notice (one month) as needed, and allow for the longer period in your programme.

Common mistakes

  • Serving only the excavation notice and missing the party structure works.
  • Underestimating the two-month party structure period.
  • Forgetting scaffolding access over the boundary (section 8).
  • Missing a second neighbour on a terrace.

When to call Coburns

Send us your plans and we will identify every notice a two-storey extension needs, serve them free of charge, and set fair access and protection terms in the award.